General and Subdivision
HPW-R1Applications on Sites with Multiple Zones, Overlays or Precincts or on Parts of Sites
Where a proposal will take place:
In two or more zones; or
Where two or more overlays apply to it; or
On a site which is partially affected by an overlay or a precinct;
then the proposal must comply with the overlay, zone and precinct rules applying to the particular part of the site in which the relevant part of the proposal is located.
When considering a proposal all relevant district-wide, overlay, zone and precinct provisions shall apply. When conflict exists between district-wide, overlay, zone and precinct provisions, the most restrictive provision shall apply, except as provided for in HPW-R1.3.
Where a proposal will take place in a precinct and a conflict exists between the precinct provisions and a district-wide or zone provision, then the provision (including any rule standards and activity status) in the precinct shall override the provision in the zone or district-wide matter chapters, whether that precinct provision is more or less restrictive. Precinct provisions do not override overlay provisions, unless it is stated otherwise in the rules.
HPW-R2Applications for More than One Activity
Where:
A proposal:
Consists of more than one activity specified in the Plan; and
Involves more than one type of resource consent or requires more than one resource consent; and
The effects of the activities overlap;
the activities may be considered together.
Different activities within a proposal are subject to different parts of the Plan, each activity will be assessed in terms of the objectives, policies and rules which are relevant to that activity.
Where different activities within a proposal have effects which do not overlap, the activities will be considered separately.
HPW-R3Rules to be Read in Conjunction with Headings and Tables
Each rule must be read, interpreted and applied in conjunction with the relevant heading, rule title and sub-heading under which is listed, and any associated table under those headings.
Each proposal must be assessed against all relevant rules and the associated headings(s) and tables(s).
HPW-R4Numerical Limits
Where any rule specifies a numerical limit using the words “up to” or “greater than”, those words must be read to mean:
The words “up to” in relation to a number include that number; and
The words “greater than” in relation to a number do not include that number.
HPW-R5Fractional Amounts
Where the calculation of any number, area or volume required by a rule results in a fractional amount:
Any fraction that is less than one-half will be disregarded and the amount of the number, area or volume will be rounded down; and
Any fraction of one-half or more will be counted as one and the amount of the number, area or volume will be rounded up.
If there are different activities within a single proposal and more than one activity requires, for the same purpose, the calculation of a number, area or volume, then all such activities must be taken together prior to any calculation and rounding.
HPW-R6Zoning of Roads, Railways and Rivers
All public roads (including state highways), railways and rivers are zoned, although they are generally not coloured on the planning maps to avoid confusion.
Where a specific zoning that is not coloured white on the planning maps within a railway then that zoning applies.
HPW-R7Application of Activity Definitions
Where an activity could be captured by more than one definition grouping classification, the most specifically defined activity and most specific rule shall over-ride the more general definition and rule.
HPW-R8Assessment of Discretionary Activities
When assessing resource consent applications for discretionary land use and subdivision activities the assessment shall include (but is not limited to) the following matters (where relevant):
The potential for reverse sensitivity effects on existing lawfully established activities and any measures proposed to avoid remedy or mitigate those effects.
The nature and location of the activity, the type and frequency of use and hours of operation.
Effects on amenity values, existing residences, visual amenity, outlook and privacy, availability of daylight, and shading.
Effects of dust, odour and other nuisance.
Effects on natural character, landscape and historic heritage values, skylines and ridges, land stability and the natural functioning of ecosystems.
Visibility from the road, road frontage domination, location of buildings, scale and bulk in relation to the site, built characteristic of the locality, colour and design of buildings, major structures and landscaping.
The cumulative effects of signs and the orientation, strength, intensity, colour and frequency of flashing of signs.
The effects of land use and subdivision on the relationship of tangata whenua with their ancestral lands, sites, water, wāhi tapu and other taonga.
The number, need, availability, location, design and suitability of parking spaces, on-site manoeuvring, queuing spaces, loading areas and access.
The safe and efficient movement of people and vehicles including traffic manoeuvring, pedestrians and cyclists, and the potential effects on the accessibility and safety of transport networks.
The need for forming or upgrading roads, level crossings and other traffic control measures in the vicinity due to increased traffic from the proposed land use or subdivision.
The need for footpaths/cycleways and kerb and channel on roads, arising from a subdivision or land use.
The necessity for street lights and the spacing and height of the lights.
The efficient provision of services to the land being subdivided, and to nearby land that might be subdivided in future.
The water system’s ability to ensure an adequate supply of potable water and the ability to meet firefighting requirements, to accommodate anticipated flows, and withstand pressures and loads.
The stormwater system’s ability to protect property and the environment from the adverse effects of surface water and its ability to accommodate the anticipated flows and withstand the anticipated loads.
The capacity, availability and accessibility of any Council wastewater system to serve the proposed subdivision and the proposed system’s ability to treat sewage and the ability to accommodate anticipated flows and withstand the anticipated loads.
The necessity, extent and location of earthworks, the proposed type of machinery to be used and the hours of operation, potential adverse effects to ecological, historic heritage and landscape values and effects on waterbodies including indigenous wetlands.
The potential for reverse sensitivity effects on existing lawfully established activities and any measures proposed to avoid remedy or mitigate those effects.
The effects of and functional need of places of assembly and emergency services to locate within the Rural Production Zone.
The impact on the transport network, taking into account the two-tier transport network hierarchy.
HPW-R9Additional Matters Over Which Control Has Been Reserved or Discretion Restricted
The following matters shall apply in addition to any matters of control or matters to which discretion is restricted in the Subdivision Chapter:
Financial contributions in the form of money or land, or a combination of these
Bonds or covenants, or both, to ensure performance or compliance with any conditions imposed.
Works or services to ensure the protection, restoration or enhancement of any natural or physical resource, including (but not limited to) the creation, extension or upgrading of services and systems, planting or replanting, the protection of Significant Ecological Areas or any other works or services necessary to ensure the avoidance, remediation or mitigation of adverse environmental effects.
Administrative charges to be paid to the Council, in respect of processing applications, administration, monitoring and supervision of resource consents, and for the carrying out of the Council's functions under Section 35 of the Resource Management Act 1991.
The duration of a resource consent, under Section 123 of the Resource Management Act 1991.
Lapsing of a resource consent, under Section 125 of the Resource Management Act 1991.
Change and cancellation of a consent, under Sections 126 and 127 of the Resource Management Act 1991.
Notice that some, or all conditions, may be reviewed at some time in the future, under Section 128 of the Resource Management Act 1991.
Whether any subdivision consent should attach to the land to which it relates, and be enjoyed by the owners and occupiers for the time being, under Section 134 of the Resource Management Act 1991.
The matters on which conditions can be imposed under Section 220 of the Resource Management Act 1991. These include: esplanade reserves and strips, amalgamation of land, holding parcels in same ownership, design of structures, protection against natural hazards, filling and compacting of land, and creation or extinguishing of easements.
Consent notices to secure compliance with continuing conditions, under Section 221 of the Resource Management Act 1991.
The design, size, shape, gradient and location of any allotment.
The location of proposed allotment boundaries and building areas so as to avoid potential conflicts between incompatible land use activities, including reverse sensitivity effects.
The location of proposed allotment boundaries, building areas and access ways or rights-of-way so as to avoid sites of historic heritage including Sites of Significance to Māori.
The provision, location, design, capacity, connection, upgrading, staging and integration of infrastructure, and how any adverse effects on existing infrastructure are managed.
The provision of reserves, including esplanade reserves and strips.
Avoidance or mitigation of natural or man-made hazards.
The extent to which the subdivision avoids adverse effects on significant flora and fauna habitats, including methods of weed and pest management and measures to control cats and dogs.
Those matters described in sections 108 and 220 of the Resource Management Act 1991.
The safe and efficient movement of people and vehicles including traffic manoeuvring, pedestrians and cyclists, and the potential effects on the accessibility and safety of transport networks.
The potential for reverse sensitivity effects on existing lawfully established activities and any measures proposed to avoid remedy or mitigate those effects.
The impact on the transport network, taking into account the two-tier transport network hierarchy.
HPW-R10Cross Leases, Company Leases and Unit Titles
Any subdivision of land by way of cross lease, company lease or unit title shall comply with the relevant zone provisions. In all staged cross-lease subdivisions, provision shall be made for servicing the building or buildings, subject to the cross-lease application and all possible future buildings on the site.
HPW-R11Limited Access Roads
Approval will be required from either the Council or the New Zealand Transport Agency, for a subdivision or new land uses proposing access to any road, including a state highway declared as a limited access road pursuant to the provisions of the Local Government Act 1974 or the Government Roading Powers Act 1989. An indication in writing, of any restrictions or conditions, from either the Council or the New Zealand Transport Agency, as relevant, should be obtained before an application for subdivision or land use consent is lodged with the Council.